Serving a Party Wall Notice

Serving a Party Wall Notice

A party wall notice gives your neighbour the details they need before building work starts. We check which notices apply, who must receive them and which drawings need to accompany them. Getting those details settled early helps you plan a start date around the correct notice period, rather than discover a problem when the builder is ready to begin.

Notices included in our award service, from £700. No VAT. Your written quote confirms the owners and work covered.

What a party wall notice is

A party wall notice is a formal written notification of proposed work covered by the Party Wall etc. Act 1996, served on the relevant adjoining owners before that work begins. Serving a party wall notice is separate from applying for planning permission or building regulations approval.

The notice identifies the proposal and starts the relevant statutory process. It is not an award, and it does not automatically authorise work after fourteen days. Your neighbour’s response, the type of notice and the applicable waiting period all matter.

Our party wall services include checking proposals and preparing notices as part of the award service, which starts from £700. Ask us for a written scope before relying on that starting price for a project with several owners.

Simple Transparent Pricing

Party Wall Notice

Free

Professional preparation and service

Schedule of Condition

from £350

Comprehensive photographic report

Party Wall Award

from £700

Complete legal agreement

Fixed fees for extensions, loft conversions, basements & new builds

Which section applies to your works

Proposed workRelevant provisionNotice normally required
A new wall at or astride the boundarySection 1A line of junction notice.
Cutting into, raising or carrying out other covered work to a party structureSection 2 rights, with notice under section 3A party structure notice.
Excavation meeting the Act’s distance and depth testsSection 6An adjacent excavation notice, with plans and sections.

More than one category can apply. A rear extension might involve both a new boundary wall and excavation near the adjoining house.

Distance alone does not decide whether excavation is notifiable. The three-metre test also considers neighbouring foundation depth; the six-metre test involves a specified downward plane from those foundations. We need suitable drawings and foundation information to assess this properly.

What a valid notice must contain

Party wall notice requirements vary with the section used. A general letter saying that builders will arrive next month is unlikely to provide the necessary detail.

  • The notice must identify the building owner and give the relevant name and address details.
  • It must describe the proposed work sufficiently for the applicable notice requirements.
  • It must state the intended start date where required.
  • The drawings and sections required for excavation must accompany that notice.
  • Proposals involving special foundations need the additional details required by the Act and separate consideration of written consent.

We check the notice and drawings against the proposed works. Planning drawings, for example, may omit the excavation depth needed for a section 6 notice. That detail needs to be available before the notice is prepared.

Notice periods: how long before you can start

NoticeNormal minimum period before the relevant work
Section 1 line of junction noticeOne month.
Party structure notice under section 3 for section 2 workTwo months.
Section 6 adjacent excavation noticeOne month.

The fourteen-day response period is different from these notice periods. Dissent does not shorten the waiting period, and the expiry of a month or two does not remove the need to settle a dispute before carrying out the relevant work.

An earlier start may be possible with the appropriate written agreement. Make that agreement explicit and check whose consent is needed; do not treat a simple consent response as permission to bring every date forward.

Who you must serve

The Act concerns adjoining owners, not simply the person living next door. Freeholders and qualifying leaseholders can both have interests requiring notice. A managing agent’s address may help with enquiries, but the agent is not automatically the owner who must be served.

Consider a neighbouring house converted into flats. There may be a freeholder and several qualifying leaseholders, with different names and correspondence addresses. The ownership and proposed work need checking before deciding which of them require notices. Joint ownership also needs attention.

Tell us about any flats, absentee landlords or company ownership you already know about. We can then identify what further information is needed instead of assuming one property means one recipient.

How the notice is served

Section 15 provides methods including personal delivery and post, with particular provisions for companies and service on an owner of premises. Keep a reliable record of what was served, on whom, how and when.

Electronic service is possible only when the recipient has stated a willingness to receive the document electronically, has not withdrawn that statement and has specified the electronic address used. An ordinary email conversation does not by itself establish all of those conditions.

The three ways your neighbour can respond

ResponseWhat happens next
Written consentAn award may be unnecessary. Check the agreed proposal, start date and continuing duties.
DissentA dispute under the Act needs the appropriate surveyor process. The owners can agree on one surveyor or appoint one each.
No written consent within fourteen daysParty structure and section 6 notices lead to a deemed dispute. A section 1 notice follows different rules.

Silence does not automatically appoint a surveyor. Section 10 contains a further appointment procedure, including a ten-day written request where the other owner neglects to appoint. The correct steps must be followed.

For a section 1 proposal astride the boundary, a lack of written consent means the building owner cannot simply build astride it. A wall wholly on their own land may be possible after the relevant period, subject to the Act.

What happens if the notice is invalid

A material defect may require a fresh notice and delay the start date. The effect depends on the error, the notice and what has happened since service. A review can establish what needs correcting before you rely on the document.

Ask for a review before starting work if the ownership details, description, drawings or service are in doubt. An award should not be treated as a way to repair every earlier error. Correcting the position before the relevant work begins is usually easier than addressing it during construction.

Frequently Asked Questions

A party wall notice formally tells adjoining owners about proposed work covered by the Act before it starts. Its requirements depend on the work, rather than on whether planning permission was needed.

The normal periods are two months for party structure notices and one month for section 1 and section 6 notices. Any dispute must also be dealt with, unless the necessary agreement permits an earlier start.

A valid party wall notice needs the details required by its section, including the relevant owner details and description of works. Excavation notices need plans and sections showing the proposed site and depth.

Yes. You do not have to employ a surveyor simply to serve a notice. Check the section, owners, content and service carefully, particularly where leaseholds or complex excavation are involved.

Every adjoining owner entitled to notice for the relevant work must be considered. That can include qualifying leaseholders as well as the freeholder; serving the occupier alone may be insufficient.

The result depends on the notice. Fourteen days without written consent creates a deemed dispute for party structure and section 6 notices. Section 1 is different, and appointment on another owner’s behalf requires further statutory steps.

Yes. Party structure and section 6 notices have statutory provisions concerning commencement within twelve months and pursuing the work diligently. Have a delayed or changed proposal reviewed before relying on old paperwork.

No single prescribed form covers every notice. The statutory content and service requirements still apply. A familiar template does not guarantee that it suits your work or identifies the correct owners.